Operation Manual / TPL65VA10 / VA30
Maintenance
5
Cleaning the compressor during
operation
5.3
Page 62
© Copyright 2016 ABB. All rights reserved.
N
ov
em
ber
2016
H
ZT
L2487_
EN
R
ev
is
ion
C
Wet cleaning using external water-pressure vessel (XC3)
Operating state prerequisites for wet cleaning XC3
NOTICE
To be able to carry out a satisfactory cleaning process which has been
tested and is recommended by ABB Turbo Systems, the following pre-
requisites must be fulfilled:
Engine load 50 ... 85%
Start of cleaning cycle in accordance with following description for
wet cleaning operation with XC3.
Compressor wet cleaning procedure with XC3
It is mandatory to fulfil the operating condition prerequisites before
cleaning compressors with XC3.
Remove the sealing plug (X).
Fill the vessel with the required volume of clean water (see the Table
of cleaning parameters).
5.3.1
Operating the water
pressure vessel