Verification of the low voltage magnitude blocking
1.
Check that the settings in the IED are appropriate, for example the
StartFrequency
,
UMin
, and the
tDelay
.
2.
Supply the IED with three-phase voltages at their rated values.
3.
Slowly decrease the magnitude of the applied voltage, until the BLKDMAGN
signal appears.
4.
Note the voltage magnitude value and compare it with the set value,
UMin
.
5.
Slowly increase the frequency of the applied voltage, to a value above
StartFrequency
.
6.
Check that the START signal does not appear.
7.
Wait for a time corresponding to
tDelay
, make sure that the TRIP signal does not
appear.
12.7.2.2
Completing the test
Continue to test another function or end the test by changing the
TestMode
setting to
Off
. Restore connections and settings to their original values, if they were changed for
testing purposes.
12.7.3
Rate-of-change frequency protection SAPFRC
Prepare the IED for verification of settings outlined in section
section
in this chapter.
12.7.3.1
Verifying the settings
Verification of START value and time delay to operate
1.
Check that the settings in the IED are appropriate, especially the START value
and the definite time delay. Set
StartFreqGrad
, to a rather small negative value.
2.
Supply the IED with three-phase voltages at their rated values.
3.
Slowly decrease the frequency of the applied voltage, with an increasing rate-of-
change that finally exceeds the setting of
StartFreqGrad
, and check that the
START signal appears.
4.
Note the operate value and compare it with the set value.
5.
Increase the frequency to rated operating conditions, and zero rate-of-change.
6.
Check that the START signal resets.
7.
Instantaneously decrease the frequency of the applied voltage to a value about
20% lower than the nominal value.
8.
Measure the time delay for the TRIP signal, and compare it with the set value.
Extended testing
Section 12
1MRK502053-UEN B
Testing functionality by secondary injection
190
Generator protection REG670 2.0 IEC
Commissioning manual
Summary of Contents for REG670 2.0 IEC
Page 1: ...Relion 670 series Generator protection REG670 2 0 IEC Commissioning manual ...
Page 2: ......
Page 16: ...10 ...
Page 30: ...24 ...
Page 58: ...52 ...
Page 62: ...56 ...
Page 76: ...70 ...
Page 90: ...84 ...
Page 94: ...88 ...
Page 108: ...102 ...
Page 246: ...240 ...
Page 252: ...246 ...
Page 267: ...261 ...