8.
Once again, wait until the stability criteria is fulfilled, then select the
Submit
button.
ICT automatically shifts to the third calibration tab,
Step3: Calibration step 3
.
9.
Remove the known fault resistance attached earlier and apply a short circuit
instead.
10. In the ICT toolbar, select the
Start reading from IED
button.
11. When the stability criteria are fulfilled, select the
Submit
button once again.
ICT automatically shifts to the fourth calibration tab,
Step4: Save calibration
factors
. Here the newly calculated k1, k2 and reference 1 are presented.
12. Check in the
Calibration result
field that all tests have been passed.
12.1. If a failure is indicated during one or more check(s), follow the
instructions/tips provided by the ICT in the
Calibration result
field.
12.2. If these tips do not solve the issue, then contact ABB Support.
IEC11000221-1-en.vsd
IEC11000221 V1 EN
Figure 13:
ICT calibration tab 4
13. Before proceeding any further make sure that you have removed the short-circuit
that was applied during calibration step 3.
14. To finish the calibration process, select the
Submit to Parameter setting
button.
15. In Parameter setting, write the newly acquired parameters to IED.
Section 6
1MRK502053-UEN B
Calibrating injection based sensitive rotor earth fault protection
62
Generator protection REG670 2.0 IEC
Commissioning manual
Summary of Contents for REG670 2.0 IEC
Page 1: ...Relion 670 series Generator protection REG670 2 0 IEC Commissioning manual ...
Page 2: ......
Page 16: ...10 ...
Page 30: ...24 ...
Page 58: ...52 ...
Page 62: ...56 ...
Page 76: ...70 ...
Page 90: ...84 ...
Page 94: ...88 ...
Page 108: ...102 ...
Page 246: ...240 ...
Page 252: ...246 ...
Page 267: ...261 ...