3.4.13 Inspection of air hoses (Foundry Prime)
General
The air hoses on Foundry Prime robots must be inspected for leakage every six
months.
Required equipment
Art. no.
Equipment, etc.
-
Leak detection spray
-
Pressure gauge
-
Cut off valve
Procedure
For this test it is recommended that the air supply to the robot has a pressure
gauge and a cut-off valve connected.
Note
Action
Recommended pressure:
Apply compressed air to the air connector on
robot base, and raise the pressure with the
knob until the correct value is shown on the
pressure gauge.
1
0.2-0.3 bar
D
C
B
A
xx1500002399
•
A: Air connection robot
•
B: Pressure gauge
•
C: Cut off valve
•
D: Air connection
It should take at least 5 seconds for the
pressure to reach 0 bar.
Close the cut off valve.
2
The time is < 5 seconds:
•
If the answer is
YES
: Localize the
leakage by following the procedures
below.
•
If the answer is
NO
: The system is OK.
Remove the leak testing equipment.
3
Pressurize by opening the cut off valve.
4
Continues on next page
148
Product manual - IRB 4600 Foundry Prime
3HAC040585-001 Revision: M
© Copyright 2013-2018 ABB. All rights reserved.
3 Maintenance
3.4.13 Inspection of air hoses (Foundry Prime)
Summary of Contents for IRB 4600 Foundry Prime
Page 1: ...ROBOTICS Product manual IRB 4600 Foundry Prime ...
Page 106: ...This page is intentionally left blank ...
Page 194: ...This page is intentionally left blank ...
Page 398: ...This page is intentionally left blank ...
Page 400: ...This page is intentionally left blank ...
Page 406: ......
Page 407: ......