1.6.2 Installation Checklist
All packing materials and restraints have been removed from each cabinet.
Each cabinet in the UPS system is placed in the installed location.
All conduits and cables are properly routed to the UPS and auxiliary cabinets.
All power cables are properly sized and terminated.
A ground conductor is properly installed.
If the cabinet does not use all module mounting locations, the provided protective covers are
installed on the front and back of the cabinet.
Battery cabinet installation instructions have been completed.
Air conditioning equipment is installed and operating properly.
The area around the installed UPS system is clean and dust-free. (It is recommended that the UPS
be installed on a level floor suitable for computer or electronic equipment.
Adequate workspace exists around the UPS and other cabinets.
Adequate lighting is provided around all UPS equipment.
Any optional accessories are mounted in their installed location and properly wired.
Summary alarms and/or building alarms are wired appropriately. (OPTIONAL)
Startup and operational checks performed by authorized service personnel.
All network connections are completed.