@2013 6Harmonics Inc. All Right Reserved
9
b) Configure the host board and GWS-3000 radio
c) Provide interface for users to manage and operate host board and GWS-
3000 radio;
d) Control the behaviors of GWS node, .e.g. set GWS Node acts as BTS or
CPE
6.2 Node Initialization
After power up, the host software will load into RAM of host board from NAND,
start to initialize and setup all the devices in good working status, including:
initialize CPU and peripheral devices.
6.3 Setup and Communicate with Host Board
There are three ways to communicate with the Host Board: a) User Interface, b)
Serial Port and c) SSH Interface.
6.3.1 User Interfaces
The host software also provides different sets of user interface for users to
configure, manage and operate the host board or radio devices and the
commands are distinguished by user commands and debug commands. User
commands are intended to allow users to change configurable parameters to
manage the host board or radio, and the debug commands are intended for
the internal design/testing engineer to perform DVT or debug or set factory
parameters.
The User Interface is the general purpose interface which should be used by
the staff of the wireless operator to perform routine maintenance and
management functions on the nodes.
6.3.2 Serial Port
Use the terminal on a PC to Connect to Host board with the following parameters:
Parameters
Baud rate:
115200
Data bits:
8
Parity:
None
Stop bits:
1
Flow control:
None
Warning: This connection is for a professional installer which has been trained
by 6Harmonics and can damage the module if performed improperly. This
connection is used to burn the first image on the host board. The module is shipped
with the latest software pre-loaded and this procedure should not need to be
performed by the customer. Only in extremely rare circumstances, such as if the
flash becomes corrupted or a power failure occurs during a remote software upgrade,