To carry out the check, it is necessary to:
1) Switch off the photovoltaic system.
2) Lower the switch of the circuit breaker, the 3000SP system will remain on but will go into error due to
no AC power supply
(or in EPS mode, if previously enabled).
4) Power up the 3000SP by flicking the AC switch up.
6) Check that the PV generation value shown on the
screen is equal to zero.
5) Check that the display shows a withdrawn power value equal to the absorbed power value which can be
measured by placing a current clamp under the import/export meter.
15. CHECKING FOR CORRECT OPERATION
OFF
ON
OFF
Waiting time 300 s
Error