Make sure that the AC circuit breaker
of the 3000SP system is open and that
no AC voltage is present at the ends of
the 3000SP.
OFF
3000SP storage system
GRID
8888
> 200W
Make sure the PV system is not producing any power on
the phase where the 3000SP system is connected, then
open the AC circuit breaker dedicated to the photovoltaic
inverter to verify that no power is being produced.
OFF
Make sure that there is a domestic load of at least 200 W. To make certain,
use a current clamp to measure the current present on the phase under the
import/export meter.
The current will enter from the grid to the utility.
Current flow
Loads
Import/Export meter
In case of
WeCo
batteries, press the POWER button of
each battery for 1 second, the RUN LED will turn on and
the internal contactor will close automatically.
Turn on the batteries:
To turn on
Pylontech
batteries: bring the switch
on the front of
all the
batteries
to the ON
position.
Press the red SW button of
a
single
battery for one second,
the internal contactor will
close automatically.
1) Unscrew the 4 screws (A) of the cover.
2) Remove the cover (B), loosen the cable gland (C), and then remove the stopper (G).
3) Pass the AC cable through the cable gland (C), and connect the phase, neutral and ground
cables to the
GRID
terminal block.
INSTALLATION OF SINGLE-PHASE SYSTEM
11.1 INITIAL SET UP PROCEDURE OF THE 3000SP STORAGE SYSTEM
10. CONNECTING THE AC - GRID POWER CABLES
Содержание Azzurro 3000SP