OFF
3000SP System
GRID
L1
L2
L3
L2 Line loads
L1 Line loads
L3 Line loads
8888
> 200W
> 200W
> 200W
Make sure the PV system is not producing power on
any phase where the PV system is connected, then
open the AC circuit breaker dedicated to the PV
inverter to verify that no power is being produced.
OFF
Make sure there is a load of at least 200 W on all three phases by using a
current clamp to measure each phase one at a time under the
import/export meter.
Current flow
Make sure that the AC circuit breaker of the 3000SP
system is open and that no AC voltage is present at the
ends of the 3000SP.
1) Unscrew the 4 screws (A) of the cover.
2) Remove the cover (B), loosen the cable gland (C), and then remove the stopper (G).
3) Pass the AC cable through the cable gland (C), and connect the phase, neutral and ground cables to the
GRID
terminal block.
INSTALLATION OF THREE-PHASE SYSTEM
14.1 INITIAL SET UP PROCEDURE OF THE 3000SP SYSTEM
13. CONNECTING THE AC - GRID POWER CABLES
Содержание Azzurro 3000SP