7.5 Trial Operation with the Servomotor Connected to the Machine
7.5.3 Operating Procedure
7-18
•
Emergency stop circuit wiring
•
Host controller wiring
Refer to the following section and change the wiring to match the system configuration.
15.1 Examples of Connections to Host Controllers
7.5.3
Operating Procedure
1.
Enable the overtravel signals.
5.12.2 Setting to Enable/Disable Overtravel
2.
Make the settings for the protective functions, such as the safety function, overtravel,
and the brake.
4.6 Connecting Safety Function Signals
5.12 Overtravel and Related Settings
3.
Set the parameters that are required for the control method you will use.
4.
Turn OFF the power supplies to the SERVOPACK.
The control power supply and main circuit power supply will turn OFF.
5.
Couple the Servomotor to the machine.
6.
Turn ON the power supplies to the machine and host controller and turn ON the control
power supply and main circuit power supply to the SERVOPACK.
7.
Check the protective functions, such overtravel and the brake, to confirm that they
operate correctly.
Note: Enable activating an emergency stop so that the Servomotor can be stopped safely should an error
occur during the remainder of the procedure.
8.
Input the /S-ON (Servo ON) signal from the host controller.
The servo will turn ON.
9.
Perform trial operation according to
7.4 Trial Operation from the Host Controller for the
on page 7-10 and confirm that the same results are obtained
as when trial operation was performed on the Servomotor without a load.
10.
Check the settings of the parameters for the control method and confirm that the Servo-
motor operates according to machine operating specifications.
11.
If necessary, adjust the servo gain to improve the Servomotor response characteristics.
The Servomotor and machine may not be broken in completely for the trial operation. Therefore, let
the system run for a sufficient amount of time to ensure that it is properly broken in.
To power
s
upplie
s
CN1, to
ho
s
t controller
To power
s
upply
CN1, to
ho
s
t controller
S
ecure the motor flange to the
machine, and connect the
motor
s
haft to the load
s
haft
with a coupling or other mean
s
.