Visual Inspection of Mechanical Connections
152315 Rev C
4–3
Visual Inspection of Mechanical Connections
To perform a visual inspection of the PV100S mechanical connections:
Visual Inspection of Electrical Connections
To perform a visual inspection of the PV100S electrical connections:
1. Ensure that the AC and DC Disconnect Switches, as well as any utility
interconnect circuit breakers or main disconnect switches, are opened.
❐
2. Ensure all anchor bolts and any required seismic bracing is properly
tightened and in place.
❐
3. Remove the wiring access panels and front covers from the AC
Interface/Transformer assembly and Main Inverter Inductor Enclosure.
❐
4. Remove the latches and open the doors of the Main Inverter Enclosure,
the AC and DC Interface Enclosures, and Communication Enclosure
and inspect.
❐
5. Verify all wire conduit fittings and connections are properly tightened.
❐
1. Ensure that the AC and DC disconnect switches, as well as any utility
interconnect circuit breakers or main disconnect switches, are opened.
❐
2. Ensure all conductors and wiring connections interfacing with the
PV100S are tightened to the correct torque value.
For specific torque values, see Table 3-1, “AC Terminal Wire Gauge,
Bolt Size, and Torque Values” on page 3–12 and Table 3-2, “DC
Terminal Wire Gauge, Bolt Size, and Torque Values” on page 3–12.
❐
3. Verify AC power conductors terminated at TB4-A, TB4-B, TB4-C
within the Main Inverter Enclosure are terminated correctly and
properly sequenced.
❐
4. Verify the AC power conductors terminated at S1-2T1, S1-4T2, S1-6T3
within the AC Interface Enclosure are terminated correctly and properly
sequenced.
❐
5. Verify DC power conductors terminated at TB3-1, TB3-2, TB3-3 within
the DC Interface Enclosure are terminated correctly and properly
polarized.
❐
Содержание PV100S-480
Страница 1: ...PV100S 100 kW Grid Tied Photovoltaic Inverter PV100S 208 PV100S 480 Planning and Installation Manual...
Страница 2: ......
Страница 3: ...PV100S 100 kW Grid Tied Photovoltaic Inverter Planning and Installation Manual...
Страница 8: ...vi...
Страница 14: ...xii...
Страница 18: ...xvi...
Страница 77: ...A Schematics Appendix A contains useful schematics to aid with installation...
Страница 78: ...Schematics A 2 152315 Rev C This page intentionally left blank...
Страница 79: ...Appendix A Schematics 152315 Rev C A 3 Figure A 1 Electrical Diagram sample...
Страница 80: ...Schematics Appendix A A 4 152315 Rev C Figure A 2 PV100S 480 Schematic for Main Power Distribution 152316 E1...
Страница 81: ...Appendix A Schematics 152315 Rev C A 5 Figure A 3 PV100S 480 Schematic for Control Power Distribution 152316 E2...
Страница 82: ...Schematics Appendix A A 6 152315 Rev C Figure A 4 PV100S 480 Schematic for Converter Control Unit 152316 E3...
Страница 83: ...Appendix A Schematics 152315 Rev C A 7 Figure A 5 PV100S 208 Schematic Main Power Distribution 152376 C1...
Страница 84: ...Schematics Appendix A A 8 152315 Rev C Figure A 6 PV100S 208 Schematic for Control Power Distribution 152376 C2...
Страница 85: ...Appendix A Schematics 152315 Rev C A 9 Figure A 7 PV100S 208 Schematic for Converter Control Unit 152376 C3...
Страница 86: ...Schematics Appendix A A 10 152315 Rev C This page was intentionally left blank...
Страница 89: ......