Commissioning
3–2
153378
Commissioning Procedure
This section provides the procedure necessary to safely and correctly commission
a GT100 inverter.
Summary
To commission the GT100:
1. Ensure the Verification Tests have been completed and have passed
successfully. See the GT100 Grid-Tied Photovoltaic Inverter Planning and
Installation Manual (Part #:153379), Section 4.
2. Begin the GT100 Commissioning Procedure as described in detail further in
this section. The steps are summarized below.
a) Record the Serial Number.
b) Inspect GT100 Inverter Enclosure.
c) Verify AC and DC Voltages.
d) Apply Grid Voltage.
e) Check the Front Panel Display.
f) Confirm Operational Parameters (AC, DC and Power Tracker).
g) Apply DC Voltage.
h) Perform the Matrix Test.
i) Operate Inverter.
3. Submit the “Commissioning Test Record” on page B–3 and Fax a copy of
product and purchase information found in “General Project and Product
Information” on page WA–4 to Xantrex.
Important:
It is important to record any issues encountered while following
this procedure.
Содержание GT100-208
Страница 1: ...Xantrex GT100 Grid TiedPhotovoltaic Inverter Operation and Maintenance Manual GT100 208 GT100 480 ...
Страница 2: ......
Страница 3: ...Xantrex GT100 Grid Tied Photovoltaic Inverter Operation and Maintenance Manual ...
Страница 8: ...vi ...
Страница 15: ...Safety 153378 xiii Figure i AC Utility Terminals Figure ii DC Terminals TB1 N A TB2 B C TB5 PV GND TB3 TB4 ...
Страница 20: ...xviii ...
Страница 22: ...xx ...
Страница 24: ...xxii ...
Страница 46: ...1 22 ...
Страница 94: ...4 14 ...
Страница 108: ...B 2 ...
Страница 110: ...B 4 ...
Страница 117: ......