Manual 26174
EGCP-2 Engine Generator Control Package
Woodward
157
14. Start another unit and allow it to parallel to the live bus.
a. Confirm phase match and synchronizer action.
b. Verify generator breaker closure.
15. Load Control
a. Verify load sharing.
b. Verify VAR/PF sharing.
16. Start additional units and parallel to the bus in the same manner as previous
units.
a. Load must be sufficient to prevent sequencing of lower priority units
off line.
b. Confirm unit address and priority settings.
c.
Adjust load control gain lower if unstable during ramp to load
sharing.
d. Adjust load share gain if unstable in load share.
17. Remove units from isolated bus one at a time by opening the auto input.
a. Verify
unload
ramp.
b. Verify
unload
trip.
c.
Verify cooldown if unit has exceeded cooldown limit.
18. When all units are off line, close mains breaker if applicable.
a. Set all units to auto for LOM detection.
This concludes the No Parallel setup.