Änderungen vorbehalten!
Subject to change without notice!
Blatt/
sheet
PM.7.002883.EN.44
Datum/
date
23.01.2013
Stand/
version
H-24.01.2017
Geprüft/
approved
WAT/MZE
Overspeed governor EOS
Operating instructions
Operational reliability of the installation is assured.
The quality and function of individual components
are subject to accurate inspection and is checked
before dispatch from our works.
The governor system should undergo an operational
test before commissioning or before possible
inspection from a technical institute.
First test run after installation
Before the first test run:
Clean the guide rails!
Clear all people and objects out of the lift
shaft before commencing the test run
Risk of crushing injuries
!
The entire lift travel path should be slowly travelled
(in inspection mode) before the functions tests is
done. Pay attention to the clearance of all fastened
parts, especially with regards to the guide brack-
ets/safety gear devices. Find and remove any pro-
truding bolts or any other potential source of dam-
age or injury in advance.
The LED states shown in chapter 5.1 - 5.3 are
only for simplification and description.
Checking the states is not necessary when
the electronic is not seeablefrom the con-
troller cabinet. This could be in case of
machineroomless elevators where the EOS is
mounted in the shaft or if the tripping direc-
tion requires the electronic to be faced
towards a wall.
5
Function testing