Chapter 7
Adjustment and initial operation
32708885 Geset 100
Version: 16.07.13
Page 39 of 77
GB
Please put the labeling system Geset 121 into operation as follows
Step
Procedure
1
If there are already exist notes of the „adjustment values“ (ref. page 37) for
the product to be labeled, the values should be available.
2
Adjust base conveyor (s. from page 40).
3
Adjust side guidance (s. from page 41).
4
Adjust wrapping unit (s. from page 44)
5
Insert label roll in labeler (s. from page 46)
6
Adjust product light barrier(s. from page 46)
7
Change peeler plateChange peeler plate (s. from page 47)
8
Positioning of peeler plate to product (s. from page 48)
9
Pitch peeler blade (Gimbal adjustment) (s. from page 50)