INSTALLATION AND COMMISSIONING CHECKLIST
Installation and Commissioning Checklist
Complete Step
Description
Manual
Section
Reference(s)
1. Pallet shipped to site from Wallace Perimeter Security (WPS).
2. Install gate onto concrete anchors; ensure all components level.
(Swing toward property side recommended.)
3. Mount operator cabinet.
4.
Complete electrical connections:
4.1
Conduit between primary and secondary columns:
4.1.1 Low voltage wiring to post termination box, excluding the
encoder and motor cables.
as above
4.2
Between the SpeedGate and the operator cabinet:
as above
4.2.1 Motor cables to be kept a minimum of 18 inches from the
secondary (control) wiring.
as above
4.2.2 Multi-conductor low voltage cable.
as above
4.2.3 Encoder cables.
as above
4.3
Between the vehicle loops and the operator cabinet:
as above
4.3.1 Vehicle detector loops leads.
as above
4.4
From operator cabinet to building:
as above
4.4.1 Power supply (2 hots, 1 ground @ 208-240V single phase).
as above
4.4.2 Control wiring.
as above; also
5. Commissioning, following mechanical and electrical portions of
the SpeedGate installation:
Содержание SPEEDGATE
Страница 48: ...48 wallaceperimetersecurity com Phone 866 300 1110 SPEEDGATE INSTALLATION...
Страница 52: ...52 wallaceperimetersecurity com Phone 866 300 1110 SPEEDGATE INSTALLATION...
Страница 59: ...PDXT PDXT C and PDTT Electrical Point to Point Diagrams 1...
Страница 60: ......
Страница 61: ...PDXT PDXT C and PDTT Electrical Point to Point Diagrams 2...
Страница 62: ......
Страница 63: ...PDXT PDXT C and PDTT Electrical Point to Point Diagrams 3...
Страница 64: ......
Страница 102: ......
Страница 103: ......
Страница 104: ......
Страница 105: ......
Страница 106: ......
Страница 107: ......
Страница 108: ......
Страница 109: ......
Страница 110: ......
Страница 111: ......
Страница 141: ......
Страница 142: ...115 Lowson Crescent Winnipeg Manitoba Canada R3P 1A6 Phone 866 300 1110 wallaceperimetersecurity com...