Series 655
INSTALLATION
979645EA
Edition 23.09.2019
35/112
4.5
Initial operation
To enable the valve cluster for pressure control setup steps 1 to 6 must be performed.
In case position control is required only it’s sufficient to perform steps 1 to 3.
Setup step
Description
1
POWER UP
Turn on ex 24VDC power supply
(and external
±
15 VDC for sensor power supply if required).
Refer to chapter «
Operation during power up
» for details.
2
VALVE
CONFIGURATION
Basic configurations of the valve must be adapted according to
application needs.
Refer to chapter «
Valve configuration
» for details.
3
INTERFACE
CONFIGURATION
DeviceNet Baud rate and Address for valve must be selected.
Refer to chapter «
Interface configuration (DeviceNet®)
» for details.
4
SENSOR
CONFIGURATION
Basic configurations of the valve must be adapted according to
application needs.
Refer to chapter «
Sensor configuration
» for details.
5
ZERO ADJUST
Compensation of the sensor offset voltage.
Refer to chapter «
Zero adjust
» for details.
6a
PRESSURE
CONTROL
CONFIGURATION
Accommodation of PID controller to the vacuum system characteristic.
Refer to chapter: «
Pressure control configuration
» for details.
6b
LEARN
For adaptive pressure controller only. Determination of the vacuum
system characteristic to accommodate the PID controller.
Refer to chapter «
Learn (adaptive control algorithm)
» for details.
Without «LEARN» or «PRESSURE CONTROL CONFIGURATION» the valve is not able
to run pressure control.