Rev: B
Vizion Install Appendix E C180, C182-
C182D, C185
TruTrak Doc: 255
18
Figure 3-8
2.34.
Apply blue threadlocker (Loctite242 or equivalent) to the threaded shank of
both MM3-300 rod ends. Rotate the pushrod until the rod end bearings on each
end are threaded in equally then tighten the jam nuts to 20-25 in-lb.
2.35.
Move the yoke throughout the full range of travel and check for binding in the
rod end bearings. If binding exists adjust the rod end bearings and jam nuts to
eliminate it.
2.36.
Ensure that aircraft stops are contacted prior to servo stops. Adjust
length of pushrod as needed until servo stops are not contacted when
controls are moved to both ends of travel.
2.37.
Verify that the servo and pushrod motion are unobstructed throughout the full
control travel. Once wiring harness is installed, ensure that the wiring harness
is properly secured to prevent interference.
2.38.
Apply torque seal to all bolts after final torqueing is achieved.