Commissioning
Mount the FP4 D carefully according to the steps described in chapter 6.2.
Depending on the scope of delivery, you must also carry out the following additional
measures for the first-time commissioning:
1. Mechanical fastening
Fix the FP4 D mechanically. Pay particular attention to the maximum tightening torques
permissible for the M5 female threads!
2. Electrical connection
Connect the FP4 D to the external controller (PLC) via the M12x1 interface using a
suitable cable.
3. Check the assembly
Make sure that the FP4 D is properly and completely assembled. In particular, the bat-
tery must be inserted and a lubricant cartridge must be fitted.
4. Execute 12 seconds control signal
Execute the 12 seconds control signal. The detailed description can be found in chapter
8.2.4. FP4 D performs a certain number of strokes and transports the lubricant from the
cartridge to the outlet.
5. Hydraulic connection
Connect the consumer hydraulically to the FP4 D. If you connect tubes to the FP4 D,
make sure that the tubes and connectors are installed tightly, cleanly and correctly.
Ideally, use tubes prefilled with the appropriate lubricant!
6. Check the settings on FP4 D
Check the basic settings of the FP4 D with the required values required for the lubricati-
on point and adjust them if necessary. Changes must be made in the PLC program.