Maintenance

36

The maintenance interval periods are stated, guidelines only. 
Any large deviations in the pattern of usage may necessitate 
further maintenance attention.

If the fan/motor assembly is going to be stored for two weeks 
before use, the fan should be rotated by hand at weekly 
intervals to avoid bearing damage.
If storage will be over one month it is recommended that the 
belts be slackened as well.
Check for soiling, damage, corrosion, and any tendency to 
bind. Clean as necessary. Check that the flexible connection 
is securely fixed. Check the function of all anti vibration 
mounts.
Check for any obstructions or blockages of the air intakes and 
discharges. Check the traps for leaks or blockages and prime 
as necessary.

Check that the fan bearing is tightened and is not unduly 
noisy, by sounding it using a metal bar as a conductor.
Where a belt guard has been supplied, check that it is fitted 
correctly.
If there is any irregular noise or knocking, renew both 
bearings. Fan bearing are greased for life, but larger units with 
standard bearings require annual lubrication. These have 
grease nipple. In the case of extreme running conditions, 
lubricate in accordance with the following recommendations:
Recommended lubricants;

ALVANIA
GREASE  3  

(SHELL) 

MOBILUX 3 

(MOBIL)

BEACON  3  

(ESSO)

SKF 28 

 

(BALL BEARING GREASE)

Inspect periodically for excessive vibration or temperature. 
Operating conditions will vary the frequency of inspection and 
lubrication. Contact the motor manufacturer or Trane for 
lubrication instruction. Most smaller frame motors come 
without grease nipple where the bearings are permanently 
sealed.
The motor with double shielded bearings are lubricated for life 
and cannot be re-lubricated.
W.E motors up to 132 frame and TECO and Brook Hansen 
motors up to 180 frame comes with sealed for life bearings, 
while motor above this range, have open bearings with “flush 
through” re-greasing facilities.

To re-lubricate the motor, complete the following:
1.

2.

3.

4.

5.

Standard condition: 8 hour operation per day with rated or 
light loading in a clean and low vibration environment. Severe 
condition: 24 hour operation per day with rated/light loading or 
in a dirty/dusty environment or where the motor is subject to 
vibration/light shock loading.
Grease Type: TECO/Brook Hansen motor – Use Esso Unirex   
Lithium N3 grease.
W.E motor – Use Shell Alvania R3 grease.

IMPORTANT

During maintenance operation the unit must be 
completely isolated and precautions taken to prevent 
any premature restart.

IMPORTANT

Do not over lubricate bearings. Excessive pressure 
caused by over lubrication can displace bearing grease 
seals or cause grease to overheat the bearing, resulting 
in premature bearing failure.

WARNING

DISCONNECT POWER SOURCE FOR MOTOR 
LUBRICATION. FAILURE TO DO SO MAY RESULT IN 
INJURY OR DEATH FROM ELECTRICAL SHOCK OR 
MOVING PARTS.

Turn the motor off. Make sure it cannot accidentally 
restart.
Remove the relief plug and clean out any hardened 
grease.
Add fresh grease through the fitting with low pressure 
grease gun.
Run the motor for few minutes to expel any excess grease 
through the relief vent.
Stop the motor and replace the relief plug.
Motor Greasing Intervals

2.  Fan

1.  Fan Motors

3.  Bearing Test

Содержание CLCP Euro 25

Страница 1: ...Installation Operation Maintenance Quantum Climate Changer Air Handlers Model CLCP Euro 25 CLCP Euro 50 CLCP Euro XP Airflow Range 1000 65 000 CFM 0 5 31 m s October 2018 IND SVN01A E4...

Страница 2: ...afe practices Indicates a situation that could result in equipment or property damage only accidents WARNING CAUTION NOTICE Important Environmental Concerns Important Responsible Refrigerant Practices...

Страница 3: ...se regulations supersede these policies Non Ingersoll Rand personnel should always follow local regulations WARNING Follow EHS Policies Copyright This document and the information in it are the proper...

Страница 4: ...ing Moving to Position On Site Forklift Truck Roller Movement LH RH Convention Foundation Erection Duct Connections External Connection Frame to Frame Connection Panel to Frame Connection Panelling Br...

Страница 5: ...QuantumTM Air Handler are Central Station Air Handlers designed for a variety of controlled air application The basic unit consists of a fan heating and or cooling coils filters and air dampers See pr...

Страница 6: ...Section 1 Type W WL 1 2 Tube H WLH 1 2 Tube A A 1 2 Tube L LL 1 2 Tube Q WLQ 1 2 Tube B AA 1 2 Tube D DL 1 2 Tube F FD 1 2 Tube S Special 21 Coil Connection L LH Side R RH Side B Both Sides X None 22...

Страница 7: ...rotected The warranty will not cover damages to the unit do to negligence during storage Indoor storage is ideal and requires only a few special precautions To protect the unit from damage due to the...

Страница 8: ...units must only be applied via the unit base frame or shipping pallet Rigging and Handling A specific lifting method for offloading the units is recommended as follows See Figure 2 1 2 3 4 5 Off Load...

Страница 9: ...Rigging and Handling 9 APPLICABLE ON ALL SECTION OTHER THAN SECTION WITH DRAINPAN APPLICABLE ON SECTION WITH DRAINPAN ONLY Figure 3 Lifting a coil section using a sling rope Figure 2...

Страница 10: ...In the case of larger units the use of several forklift trucks may be required Use extended fork lifting to prevent Drain pan damages during handling Base panel and structure damages Coil header and...

Страница 11: ...ure 9 gives recommended space allowances On the designated access side of the unit working areas must have minimum 1 mtr space P Allowance for coil connections dimension C must be dimension 200mm unit...

Страница 12: ...Heating and Air Conditioning System 90B Inlet and discharge air duct connections to the unit should be made with a flexible material minimizing noise and vibration Typically about three inches is need...

Страница 13: ...FOR CLCP 25mm FOR CLCP 50mm Assembly Installation CLCP EURO CLCP EURO XP External Connection BREAK POINT JOINING METHOD MODULE TO MODULE BREAK POINT EXTERNAL JOINING TO BE DONE AT JOB SITE 13...

Страница 14: ...Assembly Installation CLCP EURO 25 Breakpoint Frame to Frame OMS C0325_B CLCPEURO 25 Break Point Frame to Frame Joining 14...

Страница 15: ...Assembly Installation CLCP EURO 25 Breakpoint Panel to Frame OMS C0326_B CLCPEURO 25 Break Point Panel to Frame Joining 15...

Страница 16: ...Assembly Installation CLCP EURO 50 Breakpoint Frame to Frame 16 CLCPEURO 50 Break Point Frame to Frame Joining...

Страница 17: ...17 Assembly Installation CLCP EURO 50 Breakpoint Panel to Frame CLCPEURO 50 Break Point Panel to Frame Joining...

Страница 18: ...Assembly Installation CLCP EURO CLCP EURO XP Paneling 18...

Страница 19: ...19 Assembly Installation CLCP EURO XP Breakpoint ASSEMBLY INSTALLATION CLCPEURO XP BREAKPOINT INTERNAL JOINT TYPE1...

Страница 20: ...Assembly Installation CLCP EURO XP Breakpoint 20 ASSEMBLY INSTALLATION CLCPEURO XP STANDARD SECTION TO WIDER SECTION INTERNAL JOINT TYPE 2...

Страница 21: ...21 Assembly Installation CLCP EURO XP Breakpoint ASSEMBLY INSTALLATION CLCPEURO XP STANDARD SECTION TO WIDER SECTION INTERNAL JOINT TYPE 3...

Страница 22: ...Assembly Installation CLCP EURO XP CKD At Jobsite 22...

Страница 23: ...23 Assembly Installation CLCP...

Страница 24: ...Assembly Installation CLCP 24...

Страница 25: ...stallation CLCP Removing Replacing a motor CLCP 003 015 Removing shipping bracket non drive side CLCP 003 035 Apply Silicone along panel parameters prior to installing back the panel after removing sh...

Страница 26: ...the drain pan will likely overflow Figure 13 Drain Pan Trapping for module under Negative Pressure Figure 13 H 1 for each 1 of maximum negative pressure 1 J 1 2H L H J Pipe Diameter Insulation Unit Wi...

Страница 27: ...mmendation Refer to Figure 15 17 for typical cooling heating and steam coil piping Proper installation piping and trapping is necessary to assure satisfactory coil operation and to prevent operational...

Страница 28: ...as possible to the coil Vent the vacuum breaker line to the atmosphere or connect it to the return main at the discharge side of the steam trap Run the return pipe at the full size of the steam trap c...

Страница 29: ...d line OD and install it close to the condenser Minimize use of the other valves tube bends and reducers since these items tend to increase pressure drop and to reduce subcooling at the expansion valv...

Страница 30: ...cked To braze Thermostatic Expansion Valves TXV avoid direct flame figure 19 to the valve body and avoid excessive heat on diaphragm As an extra precaution a wet cloth may be around the body and eleme...

Страница 31: ...Piping and Connection Factory Supplied OFF Set Type Coil Flange Installation CLCP 030 050 For Double Coil In Single casing LL WL 4 Row Only 1 Flange Socket Weld Standard 2 Flange Socket Weld Offset Ty...

Страница 32: ...correct it 7 8 Perform the following steps prior to starting the unit 1 2 Inspect electrical connections They should be clean and secure Compare actual wiring with specific diagrams provided on the un...

Страница 33: ...USE FOR VIBRATION Fan RPM can be determined by using a strobe type tachometer or revolution counter Align the fan motor sheaves by using a straightedge The straightedge must be long enough to span the...

Страница 34: ...or ductwork Even when locked out electrically fans may cause injury or damage if the impeller is subject to wind milling The impeller should be secured to physically restrict rotational movement can...

Страница 35: ...1 gives recommended maintenance intervals for the CLCP unit Intervals are based upon normal running conditions in a moderate climate and assuming 24 hour running Units operating outside these guideli...

Страница 36: ...ion instruction Most smaller frame motors come without grease nipple where the bearings are permanently sealed The motor with double shielded bearings are lubricated for life and cannot be re lubricat...

Страница 37: ...directional arrows pointing in direction of airflow To clean permanent filters wash under a stream of water to remove dirt and lint Remove oil filter aluminium or grease filter with a wash of mild al...

Страница 38: ...r pulley or bushing installation wobbling and or damaged pulleys can unbalance a drive wear out belt rapidly and damage bearings and bend shafts Check and repair worn bearings and bent shafts Select r...

Страница 39: ...e component life and is based on fan brake horsepower requirement Check the belt tension as follows Measure the span length mm of the drive With a belt tensioner at the center of the span apply a forc...

Страница 40: ...Maintenance 40 Figure 20 Belt Tension Measurement...

Страница 41: ...th dirt preventing proper ventilation Overloaded motor Motor fan damaged Remove fan cover clean fan and replace cover Reduce load or replace with larger motor Replace motor fan clean Excessive vibrati...

Страница 42: ...Trouble Analysis 42...

Страница 43: ...43 Trouble Analysis Pulley and Belt...

Страница 44: ...Appendix A Fan and Arrangement 44 Fan Discharge Arrangement...

Страница 45: ...Appendix B Filter Layout and Quantity 45 Filter Dimension Nominal and Arrangement Flat Bag Cartridge Air Filter 6110 3130_2 page1...

Страница 46: ...Appendix B Filter Layout and Quantity 46 Filter Dimension Nominal and Arrangement Flat Bag Cartridge Air Filter 6110 3130_2 page2...

Страница 47: ...47 6110 3286_A Appendix B Filter Layout and Quantity Filter Dimension Nominal and Arrangement High Capacity Air Filter Angle Filter...

Страница 48: ...48 Appendix B Filter Layout and Quantity Filter Dimension Nominal and Arrangement HEPA AstroCel I HCX Filter 6110 3323_A...

Страница 49: ...49 6112 1853 Appendix B Filter Layout and Quantity Filter Dimension Nominal and Arrangement HEPA AstroCel VXL Filter...

Страница 50: ...Appendix B Filter Layout and Quantity Filter Dimension Nominal and Arrangement HEPA AstroCel VXL Filter 50...

Страница 51: ...Typical Motor Wiring Diagram 51...

Страница 52: ...52 Service Light and Door Switch Wiring...

Страница 53: ...Factory Installed VFD TR200 Wiring Setting 53...

Страница 54: ...Factory Installed VFD TR200 Wiring Setting 54 TR200 BASIC SETTING_OPEN LOOP...

Страница 55: ...lar maintenance of your installation by a specialist in our equipment Regular maintenance ensures that any malfunction is detected and corrected in good time and minimizes the possibility that serious...

Страница 56: ...Pre Start Up Checklist 56...

Страница 57: ...Pre Start Up Checklist 57...

Страница 58: ...crease industrial productivity and efficiency We are a 13 billion global business committed to a world of sustainable progress and enduring results For more information visit www ingersollrand com Ing...

Отзывы: