6.7 Alignment of the heat pump KITA
Templari®
Put horizontally the heat pump
KITA Templari® so that the
condensate can flow. The product must be installed with
amortized feet, purchased separately. The amortized feet
increase the height of the product, facilitating the flow of
condensate and reducing vibrations.
6.8 Probe installation
All probe used for the operation of the plant must be installed
properly in the appropriate wells using a suitable thermal paste.
WARNINGS!
Installing the probes not in a proper way will voids the warranty.
7 Hydraulic connections
7.1 Equipment control
1
Insulate wires (even underground) between product and
heating system con un isolamento resistente ai raggi UV e
alle alte temperature.
2
To avoid the transmission of vibrations on adjacent
buildings, use connection lines to product with a lenght of
at least 0,75 m.
3
If the product isn’t installed in the hightest point of heating
circuit, install then in a suitable point some additional vent
valves.
4
Remove the covers (3) from the hydraulic fittings of the
circuit.
5
Install in the return of the heating circuit, between two
shut-off valves, an anti-dirty filter to clean at regular
intervals.
6
Install a fexible pipe (1) e (6) (to be made on site) with a
gasket and a closing valve in the discharge fittings and the
riturn of the heating circuit of the heat pump.
7
Control the connection seal.
5
4
7
3
2
2
6
0,75m min.
1 Flexible connection tube in the
return of the heating to the building
(in place)
2 Gasket
3 Cover
4 Junction (Ø 1”) return of the heating
to the building
5 Junction (Ø 1”) heating supply to the
heat pump
6 Flexible connection pipe in the
heating supply towards the heat
pump (in place)
7 Insulation (in place)
WARNINGS!
If you use glycole, collect it on the
safety valve to avoid the pollution of
the environment.
The welding residues, slivers, hemp,
stucco, rust, dirt
and similar coming from the
pipelines can stand in the product
causing anomalies.
Rince thoroughtly the heat system
bifore of connecting the product to
remove possible residues!
Obligatory Y filter, contrary the
warranty will expire.
outlet
inlet
Operarate according to the rules in force, make sure the unit sia is
stably balances before of doing any operations and always adopt
sempre protection systems. The positioning indications shown
below are necessary for the correct operation of the machine,
the maintenance and the operator protection near the unit.
7.2 Particular Components
The installer has to make the choice and the installation of the
necessary components of the system, here below are listed
useful devices for the operation of the machine:
•
Shut-off valves at the entrance and exit of the circuit
allow maintenance operations senza without draining the
system;
•
Safety valve hydraulic side
•
Thermometers and pressure gauges at the entrance and
exit of the main components ensure a better monitoring
and facilitate the maintenance;
•
Vent valves in the hightest points of the system ensure the
air vent from the circuit;
•
Drain cocks in the bottom of the system to facilitate the
emptying;
•
Expansion vessel to keep the correct water pressure