39
7
Commissioning
7.1
Verify before Commissioning
Before starting up the inverter, you should check the following items for requirements.
1. Inverter unit is accessible for operation, maintenance and service.
2. Re-check that the inverter is firmly installed on to the wall.
3. Room for ventilation well is provided for one inverter or more than one inverter.
4. There is nothing left on top of the inverter heat sinker.
5. Inverter and accessories are correctly connected.
6. Cables are routed in safe place or protected against mechanical damage.
7. Specification of AC circuit breaker is reasonable.
8. Terminals not used underneath the inverter are sealed.
9. Warning signs & labels suitably affixed and durable.
7.2
Commissioning Procedures
1. Make sure all items above meet demands.
2. Close external AC circuit breaker.
3.
Rotate DC switch to the “ON” position.
Provided that there is sufficient sunlight:
−
PV arrays initialize and supply DC power to inverter;
Содержание SG2K5TL
Страница 2: ......
Страница 6: ......
Страница 10: ...IV...
Страница 16: ...SG2K5TL SG3KTL SG4KTL 31 User Manual 6...
Страница 52: ...SG2K5TL SG3KTL SG4KTL 31 User Manual 42 Press the ribbing Pull outwards Disconnect DC connectors...
Страница 60: ...SG2K5TL SG3KTL SG4KTL 31 User Manual 50 10 3 Overview of Complete LCD Menu Fig 10 1 Menu Tree...
Страница 76: ...66 Temperature Derating Curve 1 0 2 45 60 Pnom P U Ambient temperature C...
Страница 79: ......