7 Commissioning
User Manual
66
9.
Configure time according to the local time.
Time setting is very important, which directly
affects data logging.
Press
to move cursor
and
Press
to scroll up time value. Confirm the
settings by
Pressing
ENTER
. The date format is
YY/MM/DD
.
YY, MM
, and
DD
stand for year,
month, and day respectively. The time format is
hh/mm/ss
.
hh
,
mm
, and
ss
stand for hour,
minute, and second respectively.
10.
After configuring all parameters, there will be a
“setting confirmation” screen. Check whether all
above-mentioned parameters are correct.
Confirm by
Pressing
ENTER
. Cancel by
Pressing
ESC
and reset.
11.
Inverter will enter into startup process. Observe
the status of LED indicators and the LCD main
screen. If inverter‘s commissioning succeeds,
the “RUN” indicator will be lit and “RUN” will be
displayed on the “State” area.
If inverter’s commissioning fails, the “FAULT” indicator will be lit and “fault” will occur
on the display.
Press
to view “current fault” information. Remove the existing
malfunction and then repeat starting up inverter as the above procedures.