OPERATING MANUAL PAT-806 version 1.08
31
The measurement is performed similarly as in 4.5.1.
4.5.3 Three-point R
ISO
measurement on welding equipment
Keep pressing
R
ISO
button, until the screen in-
forming about the readiness for measurement
is displayed.
When parameters must be changed press
SET
. Setting is performed as in section 4.2.
Measurement parameters are set in the fol-
lowing order: U
ISO
a limit value for LN-PE
measurement
LN-PE measurement time
a limit value for LN-S measurement
LN-S measurement time
a limit value for
PE-S measurement
PE-S measurement
time, where S means shorted outputs of the
welding machine.
Connect the socket plug of the tested device into the test sock-
et of the meter, whereas the outputs to
U
1
and
U
2
sockets of
the meter.