Appendix B: Opening Conduit Drill Guides
This step may be performed before or after mounting the inverter.
The drill guides for AC grid, PV DC and battery DC are already open. If required, use this
procedure for opening additional drill guides.
CAUTION!
SolarEdge does not permit opening or puncturing the StorEdge Connection Unit
in any location other than the pre-defined drill guide locations, or otherwise
altering the construction of the enclosure, as this may compromise safety and
will void the warranty. This includes, but is not limited to, the use of fasteners
like rivets, screws, nails, inserts, or pins.
For jurisdictions requiring field applied markings on the Connection Unit
enclosure, such as labels or placards that display PV system information,
adhesive labels or placards that comply with ANSI Z535 and are compatible with
the enclosure material may be used.
ATTENTION!
SolarEdge n'autorise pas l'ouverture or la perforation du commutateur de
sécurité a tout endroit autre que les emplacements de perforation guidés
prédéfinis, ou la modification de l'enceinte électrique, car cela compromettrait
la sécurité et annulerait la garantie. Ceci inclus, sans être limité à, l'utilisation de
fixations comme des rivets, vis, clous, inserts ou des broches.
Pour les juridictions ou un marquage de sécurité est requis sur le couvercle du
coupeur DC, tels que des labels ou étiquettes qui figurent des information du
système PV, des labels ou étiquettes adhésifs compatibles avec ANSI Z535
peuvent être utilisés qui sont compatibles avec le matériau du couvercle.
For
AC connections you can use one of the following conduit openings options:
Option 1 - Connect the AC grid and backup loads wires using the AC opening (drill
guide already open; no need to open an additional drill guide). In this case use
minimum 1"(32 mm) conduit for inserting all wires.
Option 2 - Use two separate conduits: minimum 1" (32 mm) conduit for the AC grid
connection and 3/4"(25 mm) conduit for the load backup connection. In this case,
an additional drill guide should be opened for the backed-up loads.
StorEdge Solution with Backup MAN-01-00262-1.5
136
Appendix B: Opening Conduit Drill Guides
Содержание StorEdge Solution with Backup
Страница 1: ...Installation Guide StorEdge Solution with Backup For North America Version 1 5...
Страница 40: ...Figure 15 Inverter Covers Chapter 3 Installing the Inverter 39 StorEdge Solution with Backup MAN 01 00262 1 5...
Страница 98: ...Chapter 9 Setting Up Communication to the Monitoring Platform 97 StorEdge Solution with Backup MAN 01 00262 1 5...
Страница 101: ...Figure 34 Internal connectors StorEdge Solution with Backup MAN 01 00262 1 5 100 Communication Connectors...
Страница 141: ...Figure 47 The battery holder StorEdge Solution with Backup MAN 01 00262 1 5 140 9V Battery Replacement...