1 Position and Orient System Components
Identify the best location for each component of the AES, keeping in mind the length of all cables
that will be used to connect all of the components. These lengths may vary if using cables other than
the ones supplied by Solar Stik.
Figure 20. Working-space radius for the AES
25’
30’
100’
PAMs
MEP-802A
PSS-G/RAID
Tower
Power
management
and energy
storage
components
• The PV arrays must be within 30’ of the Power Hub 2400. (Extensions are available.)
• The MEP-802A TQG must be within 25’ of the PRO-Verter 7000 AGS.
• The PSS-G/RAID Tower must be within 100’ (verify cable lengths) of the PRO-Verter
7000.