Start Operation
Section 2 - Operation
2.5-12 Electrical Inverter (If Equipped)
1.
Turn the emergency main power disconnect switch
to the “ON” position.
2.
Make sure the ON/OFF switch of the inverter is “ON.”
3.
Inverter activation is indicated by a glowing green
LED on the front of the inverter.
Caution
The emergency main power disconnect switch
MUST be turned OFF at the end of the shift or
the batteries will drain.
2.5-13 Shutdown Procedure
1.
Completely lower the platform.
2.
Push in emergency stop button located on
operator’s control box.
3.
Turn BASE/OFF/PLATFORM select key switch to
“OFF” position and remove the key from the
control box.
Warning
Ensure that you maintain three points of contact
when using the ladder to mount/dismount
the platform.
4.
Dismount the platform using the ladder.
5.
Turn emergency main power disconnect switch
to “OFF” position.
2.5-11c Retracting the Outriggers
1.
Ensure the emergency stop button is pulled out.
2.
Select “PLATFORM” position with BASE/OFF/
PLATFORM select key switch.
3.
Select the “LIFT” position with LIFT/OFF/DRIVE
select key switch.
4.
Lower the aerial platform.
5.
Select and hold the outrigger enable toggle switch
in either the “UP” or “DOWN” position, then push
and hold pairs (front or rear) of outrigger UP/DOWN
toggle switches to “UP” position until the outriggers
are fully retracted.
Note
Limit switches are used to protect the outriggers
from being damaged. If aerial platform will not drive,
visually check to see that ALL outriggers are fully
retracted.
Warning
If alarm sounds during operation, the aerial platform
is not level or an outrigger does not have firm
ground contact. Lower the platform immediately!
Make the necessary adjustments to level the aerial
platform.