Maintenance and service
5.3 Adapting a project (Upgrading the project / Replacing the SIMOTION controller)
SIMOTION D410
Commissioning Manual, 02/2012
175
Additional references
For further information, refer to the
SIMOTION SCOUT Configuration Manual.
5.3.4
Upgrading a user project to the new SCOUT version
Prerequisite
It is essential that a backup copy be made of the original project before the upgrade,
because the data storage of the project is also upgraded during the upgrade. This ensures
that you can always return to the original project if the upgrade fails (power interruptions,
unexpected faults, incorrect operation, etc.).
Procedure
1.
When opening the project a window appears with a message that the project to be
opened was created with another SCOUT version, as well as a prompt as to whether the
upgrade should be performed.
Confirm the prompt with "OK".
Figure 5-6
Prompt as to whether the project should be upgraded
2.
After the conversion another prompt appears as to whether the project should be opened
write-protected. Confirm this prompt with "No" for a version upgrade (do not open write-
protected).
Figure 5-7
Prompt as to whether the project should be opened as write-protected
Do not open as write-protected:
The project can be edited. The data in the controller and in the project is not consistent after
going online. Diagnostic functions cannot be executed directly. The project must be loaded
to the controller first.
Содержание SIMOTION D410
Страница 12: ...Table of contents SIMOTION D410 12 Commissioning Manual 02 2012 ...
Страница 160: ...Commissioning software 4 18 Configuring Safety Integrated functions SIMOTION D410 160 Commissioning Manual 02 2012 ...
Страница 212: ...Diagnostics data 6 3 Additional service and diagnostics options SIMOTION D410 212 Commissioning Manual 02 2012 ...