127/166
Siemens Building Technologies
Basic Documentation RVA47.320
CE1P2379E
HVAC Products
Description of the OEM settings
15.07.2002
Cascade settings
6.4
Cascade management strategy
•
Selection of required type of lead boiler operation.
Combination with optimum running time strategy.
For the plant configuration used, this setting represents an optimum combination of
lead boiler operation and running time strategy.
1. Press the line selection buttons to select line 50OEM.
2. Press the + / - buttons to select the required combination of lead boiler operation
and running time strategy.
Setting range
Unit
Factory setting
1...6 1
2
There is a total of 2 types of lead boiler operation and three running time strategies
available. The 6 combinations are assigned as follows:
Einstellung (Kombination)
type of lead boiler operation
running time trategyrunning
1
autonomous
1
2
autonomous
2
3
autonomous
3
4
linked
1
5 (Standard setting)
linked
2
6
linked
3
Proceed as follows to make the required setting:
- First, determine the required type of lead boiler operation
- Determine the required running time strategy
- Use the above table to choose the setting required for your application
Benefit
Description
Setting
Note