5.6.2
Overview of the installation steps (duct-side preparation)
Step
Procedure
Reference
1
Installing the flange with tube.
see "Installing the flange with tube",
page 31
2
Installing the connection unit.
see "Installing the connection unit",
page 32
3
Fitting the purge air unit or units.
see "Installing the Ex purge air unit",
page 34
4
Observing protective gas discharge line (con‐
nection unit).
see "Protective gas outlet", page 33
.
5
Connecting pressure, temperature and purge
air monitor.
see "Connecting pressure, temperature
and purge air monitor", page 46
.
6
Connecting protective gas feed to SR-unit.
see "Connecting protective gas to the
SR-unit", page 54
5.6.3
Installing the flange with tube
DANGER
Hazard through hot, explosive or toxic flue gases
Hot and/or noxious gases can escape during installation work on the gas duct, depend‐
ing on the plant condition.
b
Work on the gas duct may only be performed by skilled persons who, based on
their technical training and knowledge as well as knowledge of the relevant regula‐
tions, can assess the tasks given and recognize the hazards involved.
CAUTION
Device damage due to defective/missing insulation of the channel in case of hot
measuring channel
b
When the gas duct is hot, insulate the duct and flanges so that the GM32 is pro‐
tected from high temperatures.
Installing the flange with tube on the gas duct
1
Cut openings on the gas duct for the flange with tube.
2
Insert the flange with tube. Pay attention to the following:
°
The "Top" marking must point upwards vertically, irrespective of the gas duct
angle.
°
The tube must project at least 30 mm into the gas duct.
1
200
18
4 5
°
Figure 8: "Top" marking on flange with tube
1
"Top" marking
3
Attach the flange with tube.
MOUNTING
5
8015558/YYJ8/V1.7/2016-07 | SICK
O P E R A T I N G I N S T R U C T I O N S | GM32-Ex
31