NOTE
The measuring probe must not collide with other devices or fittings.
4
Tilt the tube slightly downwards (max. 1°) to allow any condensate to drain off.
5
Now fix the flange with tube properly to the gas duct. Make sure that the align‐
ment of the flange does not change.
6
If necessary, attach duct insulation to protect the device from heat.
5.6.4
Installing the connection unit
1
Figure 9: Connection unit for GM32 Ex
1
Connection cable only for version 2G
•
The line lengths to the GM32 sender/receiver unit are according to project plan‐
ning.
b
Install the connection unit using the 4 threaded bolts according to project plan‐
ning. Dimension drawing,
.
NOTE
Do not make the electrical connection to the connection unit yet.
5.6.4.1
Installing the Ex interface relay (for version 2G)
NOTE
For more information, see the Ex Interface Relay (SR852) Manual.
5
MOUNTING
32
O P E R A T I N G I N S T R U C T I O N S | GM32-Ex
8015558/YYJ8/V1.7/2016-07 | SICK