SENS EnerGenius® DC Compact Technical Manual
38
Boost by 2% of Float setting, must be
less than 40% higher than Boost setting
Overvolt Fault
Adjust setpoint to trigger Over Voltage
Shutdown alarm, must be greater than
High DC setting
Low Current
Adjust setpoint to trigger Low Current
alarm from 0% to 50% of nominal
current
Battery Set-up
Battery Select
(type)
Select type of battery to be charged -
flooded lead-acid, AGM, nickel-cadmium
VRLA, power supply.
Battery Select
(cells)
Adjust number of series cells in battery
string
Batt Commission
(voltage)
Adjust battery commissioning output
voltage must be greater than or equal to
Float voltage
Batt Commission
(current)
Adjust battery commissioning output
current from 5% to 100% of nominal
current rating
Batt Commission
(duration)
Adjust battery commissioning hours
from 1 to 120 hours
Batt Commission
(enable)
Start or stop commissioning cycle.
Charger will deliver commissioning
voltage and current until commissioning
hours expire.
DC Start Volts
Adjust DC Startup Voltage. Set to zero to
start into zero-volt battery
automatically.
Force Startup
Enables charger to attempt to charge a
battery with a voltage below the DC
Startup Voltage.
Restore Factory Default Settings
Restore settings to factory configuration
Other Settings
LCD Brightness
Adjust LDC Brightness from 0
–
100%
Minimum System Number of
Chargers
Enable or disable whether alarm is
indicated or not. Alarm active when the
number of charger modules active on
SENSbus is less than the minimum
charger count. Disabled by default,
meaning no alarm. See Error Code 301
for further details.
Battery Check
Battery Check
Start or stop a manual Battery Check.
Batt Check Time
Adjust amount of time to run Battery
Check from 1 to 60 minutes
Batt Check Vmin
Adjust minimum voltage allowed during
Battery Check test, must be greater than
End-of-Discharge voltage and less than
98% Float voltage