5.
INBUILT INTO ISLAND WALL
NON COMBUSTIBLE SURROUNDING
STEP 1: BASE
Lay a masonry base, minimum 75mm thick (ie. Solid bricks).
The base should be laid on an adequate ground capable of
supporting it’s weight.
STEP 2: SHEET METAL LAYER
(OPTIONAL STEP)
Place a piece of sheet metal on top of the masonry base, this
will level the base and enable you to safely manoeuvre the
firebox.
Allow a minimum of 100mm on all sides if possible.
STEP 3: SIDE FRAMES
Place a steel frame (minimum 51mm thick) on either side of
the enclosure. Remember to leave a 25mm air gap on the sides
of the appliance.
**IMPORTANT**
It is strongly recommended that the steel frame allows for a
distance of 300mm to the ceiling, this allows the cavity lid to
be placed directly above and stop heat from traveling above the
lid via the frame.