![Schweitzer Engineering Laboratories SEL-351A Скачать руководство пользователя страница 363](http://html.mh-extra.com/html/schweitzer-engineering-laboratories/sel-351a/sel-351a_manual_1216694363.webp)
Date _______________
Date Code 20080213
Instruction Manual
SEL-351A Relay
SET.11
of 32
SEL-351A Settings Sheets
Relay Settings (Serial Port Command SET and Front Panel)
Phase-to-phase undervoltage pickup
(OFF, 0.00–300.00 V secondary)
27PP
=
Phase-to-phase undervoltage pickup
(OFF, 0.00–300.00 V secondary)
27PP2P
=
Phase-to-phase overvoltage pickup
(OFF, 0.00–300.00 V secondary)
59PP
=
Phase-to-phase overvoltage pickup
(OFF, 0.00–300.00 V secondary)
59PP2P
=
Synchronism Check Elements (See
and
(Make the following settings if preceding enable setting E25 = Y.)
Voltage window—low threshold (0.00–300.00 V secondary)
25VLO
=
Voltage window—high threshold (0.00–300.00 V secondary)
25VHI
=
Maximum slip frequency (0.005–0.500 Hz)
25SF
=
Maximum angle 1 (0.00°–80.00°)
25ANG1
=
Maximum angle 2 (0.00°–80.00°)
25ANG2
=
Synchronizing phase
(Global setting PTCONN = WYE: VA, VB, VC or 0° to 330°
in 30° steps; degree option is for VS not in phase with VA,
VB, or VC—set with respect to VS constantly lagging VA)
(Global setting PTCONN = DELTA: VAB, VBC, VCA or 0°
to 330° in 30° steps; degree option is for VS not in phase
with VAB, VBC, or VCA—set with respect to VS
constantly lagging VAB)
SYNCP
=
Breaker close time for angle compensation
(0.00–60.00 cycles in 0.25-cycle steps)
TCLOSD
=
Frequency Element (See
–
(Make the following settings if preceding enable setting E81 = 1–6.)
Phase undervoltage block (25.00–300.00 V secondary)
27B81P
=
Level 1 pickup (OFF, 40.10–65.00 Hz)
81D1P
=
Level 1 time delay (2.00–16000.00 cycles in 0.25-cycle steps)
81D1D
=
Level 2 pickup (OFF, 40.10–65.00 Hz)
81D2P
=
Level 2 time delay (2.00–16000.00 cycles in 0.25-cycle steps)
81D2D
=
Level 3 pickup (OFF, 40.10–65.00 Hz)
81D3P
=
Level 3 time delay (2.00–16000.00 cycles in 0.25-cycle steps)
81D3D
=
Level 4 pickup (OFF, 40.10–65.00 Hz)
81D4P
=
Level 4 time delay (2.00–16000.00 cycles in 0.25-cycle steps)
81D4D
=
Level 5 pickup (OFF, 40.10–65.00 Hz)
81D5P
=
Содержание SEL-351A
Страница 10: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 16: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 34: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 126: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 184: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 198: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 228: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 278: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 384: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 410: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 450: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 454: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 472: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 504: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 558: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 562: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 586: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 608: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...
Страница 666: ...This page intentionally left blank Courtesy of NationalSwitchgear com ...