You Will Need:
Philips head screwdriver
1. Remove the boiler’s front panel by removing the four screws that secure the panel.
3. Confirm whether all heat emitters and pumps are
connected to the piping system.
4. Fill the boiler to a minimum of 20 PSI (138 kPa) water
pressure and a maximum of 30 PSI (207 kPa).
5. The deaeration process takes approximately 15 minutes
for completion.
After 15 minutes, the display will show “End” (see right
image). The commissioning process is complete.
6. On the PC Board, press the black button again to resume
normal operation mode.
7. Operate the domestic hot water or central heating to
ensure the boiler operates properly.
8. Close the air vent on the pump. After approximately one
week, all air in the system should be eliminated via the air
separator in the piping system.
DIP Switches
PC Board
Note: Alternately, on initial installation, you may press and hold
the DHW button then simultaneously press the CH button on the
control panel instead of removing the boiler’s front panel.
2. On the PC Board, press and hold the top, left black button shown below. The Maintenance
Required icon (see right image) on the controller display will appear.
Содержание COMBI i060C
Страница 124: ...124 Rinnai I Series Condensing Boiler Combi Manual ...
Страница 125: ...Rinnai I Series Condensing Boiler Combi Manual 125 ...
Страница 134: ...134 Rinnai I Series Condensing Boiler Combi Manual ...
Страница 135: ...Rinnai I Series Condensing Boiler Combi Manual 135 ...
Страница 136: ...136 Rinnai I Series Condensing Boiler Combi Manual 800000111 3 2019 ...