Installation examples
This type of installation (See Fig.1) requires an insulated chimney
pot, even if the entire conduit is installed inside the building.
Besides, the structure must be inserted into a properly ventilated
cavity wall.
In the lower part of the chimney pot there is an inspection cover,
properly isolated from wind and rain.
Protection from rain
Fig.1
Grille for air passage into the
skylight shaft with opening for
inspecting the chimney
Cavity wall
T fitting for condensation
Insulated chimney
It is prohibited to install a 90° bend for the initial segment, since
the ashes would quickly obstruct smoke passage, causing
draught problems in the boiler. (See Fig. 2)
Ashes deposited in the
90° bend
NO
It is possible to use an existing chimney or a shaft via ducting.
For this type of installation the standards on ducted smoke
evacuation systems must be complied with. In the lower part
of the chimney pot, inside the home, there is a “T” type fitting
installed; externally there is another one installed, so that the
outside section can be inspected.
It is prohibited to install two 90° bend, since the ashes would
quickly obstruct smoke passage, causing draught problems in
the boiler. (See Fig. 2)
Smoke duct:
use of a non-insulated
tube
T Fitting
Insulated chimney
Fig.3
Protection from rain
T fitting for condensation
Combustion ashes collection
c condensation cap
Combustion ashes collection
c condensation cap
External air
intake
External air
intake
External
air intake
Содержание HR EVO 200 SMART
Страница 2: ......