7
RAM 100 • 1000 • 5500
RAMSET
www.ramsetinc.com
24”
4”
MIN
4”
6 1/2”
5 3/4”
5”
3” MIN
GATE
WALL
Conduit for
Master-Slave
Conduit for
power
Conduit for low
voltage wires
18” x 18” x 24”
Concrete Pad (minimum)
TOP VIEW
GATE
SHOWN OPEN
LH
FRONT
INSTALLATION
Wall
GATE
4”
4” MIN
GATE
6”
7 1/4”
11 3/4”
BASE
OPERATOR
concrete 18”
(minimum)
concrete 18”
(minimum)
24”
TAIL
4 1/2”
2 1/2” MIN
4”
TOP VIEW
GATE SHOWN CLOSED
LH
FRONT INSTALLATION
CL
Mark centers and
install four 1/2-13
UNC Red-head
Anchor Bolts
Wall
Figure 1
Figure 2
Figure 3
CONCRETE PAD CONSTRUCTION
Dimensions given for the pad are based on soil bearing
shear of 2000 P.S.F. These figures may have to be ad-
justed depending on local soil conditions.
1. Construct form for mounting pad according to dimen-
sions shown in Figure 1, 2 and 3.
2. Locate mounting pad according to dimensions given in
illustration.
3. Level top edge of form.
4. Set reinforcing bars and wire mesh.
5. Mix concrete, pour mixture into form. Level and finish
surface after pouring is complete.
6. Allow pad to cure for 48 hours, and remove forms.
All Sliding Gate Operators are factory preset for
(LH) Left Hand Installations. RAM 100 is for front
installation only.
RAM 100 INSTALLATION SPECIFICATIONS
WARNING
Do not exceed the specifications. The warranty on your unit will be void if the
installation exceeds the recommended specifications.