Chapter 6
Installation and Testing
6.1 Unpacking check-up
Check whether the type of device, spare parts and number are same with that of packing list. Make
sure the device appearance is in excellent condition. There must be drying process if the device has
been damp.
6.2 Preparation before installation
a.
Read this manual carefully
b.
Verify all the cables are good for normal use. (Please refer to relative chapter for the connection
method of cables).
c.
Make sure that the voltage of power supply is within the range and grounding protection.
d.
Preparing the bit error rate test and optical power meter for necessary line tests.
e.
For the devices to be installed, please consider their positions and the length of cables. We
recommend you have a whole topology first.
6.3 Installing process
6.3.1
Fix the device
RC3000 can be installed in the chassis or on rack. Please make sure that the installation is firm and
convenience for operation.
6.3.2
Connecting cables
a. Connect the power supply and ground:
There are both AC power supply and DC power supply of RC3000, no matter which kind of power
supply make sure of good grounding protection. And the chassis grounding of RC3000 must be
connected to that of other device and the earth. Otherwise the device may not work normally.
b. E1 signal interface:
The E1 interfaces of RC3000-2E1 are CC3 interfaces, and the E1 interfaces of RC3000-4E1 are
RJ45 balanced E1 interfaces. Please use the attached cables we offered, and when you need to
transfer balanced interfaces to unbalanced ones RC909-4E1 of Raisecom is available.
c. Optical interface:
SC connector is for optical interface. And if you are not sure of Rx & Tx direction, please connect
the connector before device powered on.
d. Connect network management interface: