Installation Guide / ComT 2.0: 5°, 10° and 15°
13
Code-Compliant Planning and Installation Guide V1.0 - Complying with AS/NZS1170.2-2011 AMDT 2-2016
In case of large purlin spacing, MT-Rail Support with T50 or T110 Rail will be an option. Please follow the steps below.
2. MT-Rail Support with T50/T110 Rail Installation (optional)
5.2.1 Based on the rib spacing of the metal roof
sheet, mark out the positions of self-tapping screws
on the MT-Rail Support and then attach the glued
EPDM rubber pad under the MT–Rail Support as
shown in Figure 5 (Clenergy 240 mm long MT rail
section is supplied with two Buildex 14-11 x 70 Hex
Head Zips screws).
Insert half of Splice
into T Rail
Two sets of
Self-tapping screws in
each side of T Rail
Insert the other half of
the Splice into T Rail
Two sets of Self-tapping
screws in each side of T Rail
- Installation Instructions -
Figure 5
Figure 6
Figure 7
Figure 9
Figure 8
5.2.2 Confirm the position of the purlin for the
MT-Rail Support installation, then fix the MT Rail
Support by screwing through two ribs on the purlin
as shown in Figure 6.
5.2.3 Fix the Rail onto the MT-Rail Support with T-Rail Clamps as shown in Figures 7 and 8.
Recommended torques of M8 Bolt:16-20N•m
5.2.4 If the T Rail is not long enough, please use Splice for T Rail to connect two T Rails together. Insert half of the Splice
into T Rail and fasten with two sets of Self-tapping screws in each side of the T Rail, and then insert the other half of
the Splice into T Rail and fasten with Self-tapping screws as shown in Figure 9.