Installation Guide / ComT 2.0: 5°, 10° and 15°
12
Code-Compliant Planning and Installation Guide V1.0 - Complying with AS/NZS1170.2-2011 AMDT 2-2016
Installation Instructions
- Installation Instructions -
When using the Tin Interface (ER-I-05 as an example) with the ECO Rail
solution, please follow the steps below.
5.1.3 To connect several rails, slide half of the splice into the rear side of the rail. Fasten the first M8 Bolt using an Allen
key, and slide the next rail into the splice as shown in Figure 4. Tighten the second M8 Bolt using an Allen key. The total
rail length is recommended not to be over 30 meters considering the rail’s thermal expansion problem.
M8 Bolt Recommended torque is 10 ~12 N•m.
Splice provides an electrical connection between the 2 rails through the pressure bolts. This eliminates the need of
using 2 earthing lugs.
Note: It is important to run visual inspection to make sure installations above were properly done. It is important to
check and correct fasteners torques with torque wrench or similar tool if using tools without torque setting during
installations.
1. Tin Interface with ECO Rail Installation
5.1.1 Fix the Tin Interface on the metal purlin with a self-tapping screw
according to the installation plan (Clenergy Tin interface is supplied
with one Buildex 14- 11 x 70 Hex Head Zips screw). Ensure that the Tin
Interface in the front and rear or left and right directions are aligned
using string as shown in Figure 1.
5.1.2 Fix the Rail on the Tin Interface as shown in Figures 2 and 3.
Recommended torques of M8 Bolt:16-20N•m
Figure 1
Figure 2
Figure 3
Figure 4