PFT continuous mixer HM 2002 Overview - Operation - Spare parts lists
Disassembly
40
2017-03-14
38.4 Actions after completed maintenance
1. After finishing the maintenance works and prior to switching on
the machine, the following steps have to be carried out:
2. Check all previously loosened screw connections for secure fit.
3. Check if all previously removed safety systems and covers are
properly reinstalled.
4. Ensure that all used tools, materials and other equipment were
removed from the work area.
5. Clean the work area and remove any spilled materials such as
liquids, processing material or similar.
6. Ensure that all safety systems of the installation work perfectly.
39 Disassembly
After the useful service life has been reached, the device has to be
dismantled and disposed of in an environmental-friendly manner.
39.1 Safety
Personnel
Disassembly must be carried out only by specially trained
technical personnel.
Work on the electrical system must be carried out by qualified
electricians only.
Basic information
WARNING!
Risk of injury in case of improper disassembly!
Stored residual energies, sharp components, points
or edges at and inside the device or at the required
tools might cause injuries.
Therefore:
Prior to starting the works ensure that there is
sufficient space.
Carefully handle components with sharp edges.
Ensure order and cleanliness at the working place!
Loose components and tools on top of one
another or lying about pose potential accident
risks.
Dismantle components correctly. Pay attention to
partly high dead weight of the components. If
required use lifting equipment.
Secure components that they do not fall down or
fall over.
In case of doubt, consult the dealer.