4-1
Section 4
Cabling the System
Labels and cable ties are included with your order to use when cabling the system.
During the cabling process, mark the labels with the appropriate identification, such as
the cell number, power supply number, and power source location, and then attach the
labels to both ends of each cable.
4.1. Power Cabling for 100V to 120V Systems
Use the following procedure to connect component power cables:
1. Connect the cell power cables to the cell.
2. Route the power cables down the right side of the cable manager and exit the
bottom of the cabinet as shown in
Figure 4-1
. After all power cables are routed,
secure the cables to the cabinet frame using cable ties.
Do not connect the cell power cables to the premises wiring at this time. Cell power
cables are connected to the premises wiring during
5.3 Apply AC Power Initially
.
Содержание NECCare Platinum Express5800/A1160
Страница 1: ...EXPRESS5800 A1160 HW Installation Guide ...
Страница 8: ......
Страница 14: ......
Страница 28: ......
Страница 36: ......
Страница 41: ...Power Cabling for 200V to 240V Systems 4 5 4 2 1 Power Strip Cabling for a System with One Cell ...
Страница 42: ...Power Cabling for 200V to 240V Systems 4 6 4 2 2 Power Strip Cabling for a System with Two Cells ...
Страница 52: ......
Страница 76: ... 456 01805 000 ...