Order of unpacking
The unpacking process requires that the following procedures be
completed in the order shown:
1. Identify the equipment
2. Unpack the RF Cabinet
3. Unpack the Power Cabinet
4. Inspect the equipment for damage
Equipment Identification
Use Figure 3-1 and Figure 3-2 to visually identify the SC 4812ET RF
and Power Cabinet, respectively.