
Apr 2001
V06.03
119
SC
TM
4812ET RF and Power Cabinet Hardware Installation Manual
DRAFT
Chapter 6: What’s Next and Cleanup
This section includes...
Introduction
119
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Cleanup the Site
119
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Fill out Checklist
120
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Optimize the System
122
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Tables
Table 6-1: Installation Completion Checklist
120
. . . . . . . . . . . . . . .
Introduction
Before Optimization/ATP performed, complete the following
procedures:
– Clean up the site.
– Fill out the installation completion checklist.
Cleanup the Site
It is important that all shipping and installation materials to be discarded
be removed from the customer site. Return all tools to their proper place
and conduct a final inspection.
Remove Protective Covering
Remove any antistatic plastic or cloth sheeting that was used to cover the
equipment.
Pickup tools and leftover materials and debris
– Place all hand and power tools in the installation tool kit or other
appropriate place. Note any tools that need replacement, cleaning,
or adjustment.
– Place any leftover materials in a location specified by the site
manager.
– Remove any packing material.
– Ensure that all scrap materials have been removed from the site.
Environment
– Check that the power connections are tight.
. . . continued on next page
6