9.2.1
Installing Cabling Guide Brackets for Switches with HyperScale Fabric
Boards
The HyperScale chassis must be pre-installed in the rack with the 2 x 19" long bracket.
The cabling guide bracket for HyperScale Fabric Boards is installed on the 4700 rack’s front
rail, in a horizontal position, in parallel and between two HyperScale switches.
To install a cabling guide bracket for HyperScale fabric boards:
Install the cabling guide bracket at the front of the rack, under the rail kit, on the rack itself
between the two 4700 using four screws to secure the bracket in place.
Figure 36: Cable Management for Switches with HyperScale Fabric Boards
9.2.2
Connecting the InfiniBand Cable between Fabric Boards
To connect a cable between Fabric Boards:
1.
In a Fabric Board installed at the top chassis, position the InfiniBand cable connector with
the pulling tab at top, and push the connector in place.
2.
Route the cable straight down to the nearest cabling guide bracket hanger position.