Installation
5.2
Installation process
5.2.1
Determination of the installation position
The position of the axle and the tensioning device of the secondary
cleaner must be determined on both sides of the chute wall. In this
process, the positions are therefore determined for where the shaft
of the secondary cleaner is routed through the chute wall and/or
where the tensioner is installed on the chute wall.
The secondary cleaner is delivered jointly with a tensioner. This is
delivered as a work´s dismantled unit and will be installed together
with the secondary cleaner during the general installation.
The installation process for the secondary cleaner and the tensioner
is described in the supplied installation instructions.
An overview of the installation steps follows:
Various on-site conditions requiring different work steps are
possible for the installation. These are presented as follows:
Installation on an encapsulated transfer system
•
Follow the instructions given in Section 5.2.2.
Installation on an encapsulated transfer system with pre-existing
installation openings and air line brackets for belt cleaners.
•
Follow the instructions given in Section 5.2.3.
Installation on an open transfer system
•
Use the equipment provided at the site to comply with the
dimensions for correct installation.
No.
Installation step
Instructions
1
Determining the installation position
M3289
2
Installing the cleaner
M3289
3
Installing the tensioner
M3289
4
Tightening the cleaner
M3289
Tab. 1: