Fire damper - FDMR
Page 58
Version 2023-06-15
TPM 140/19
1
FDMR
2
Solid ceiling construction
3
Mortar or gypsum
4
Insulation board made of mineral wool, with a surface treatment of aluminum foil, min. density 66 kg/m³ (System ISOVER Ultimate Protect Wired Mat 4.0
Alu1)**
5
Standard air duct, made of galvanized sheet metal min. thickness 0,8 mm
6
ISOVER Protect BSK glue - apply on the insulation and fix it to the fire separation construction
7
Clamp with threaded rod
Ø
D
min.
Ø
D+80
max.
Ø
D+300
X
≥
1
1
0
*
X
EIS 60
EIS 90
≥
1
1
0
*
40...1
50
v
a
ri
a
b
le
≥
100 **
40...150
* min. 110 mm - Conrete
min. 125 mm - Aerated concrete
■
For connection of following duct
■
Minimum and maximum distance between the ceiling and fire damper is unlimited
■
When installing the insulation, follow the ISOVER manufacturer's instructions
■
The damper and the duct must be suspended separately
■
The duct must be suspended on both sides of damper acc. to national rules
■
Duct between fire damper and fire separating construction must be suspended by using threaded rods and mounting profiles, or another
mounting system acc. to national standards
■
Load of the suspension system depends on weight of the fire damper and duct system
■
Max. distance between two suspension systems is 1500 mm
■
Following air-conditioning duct must be suspended or supported so that all load transfer from the following duct to the fire damper is absolutely
excluded. Adjacent duct must be suspended or supported, as required by the duct suppliers
■
If the threaded rod is located inside the duct insulation, distance between threaded rod and duct is max 30 mm
■
If the threaded rod is located outside the duct isolation, distance between threaded rod and isolation is max. 40 mm
Outside solid ceiling constrution - ISOVER Ultimate Protect - mortar or gypsum (damper above ceiling)
** EIS 60
for DN 100 – DN 800 - thicknes 100 mm
EIS 90
for DN 100 – DN 315 - thicknes 120 mm (2x60 mm)
EIS 90
for DN 350 – DN 800 - thicknes 160 mm (100+60 mm)