Wiring the Wallbox Power Module with DALI Control Unit:
Line/Mains Voltage Wiring Details

Wallbox Power Module Installation and Operation Guide   3

®

• Use properly certified cable for all line 

voltage/mains cables.

• Proper short-circuit and overload 

protection must be provided at the 

distribution panel.

• Install in accordance with all local and 

national electrical codes.

• IEC PELV terminals may be temporarily 

unplugged for ease of IR, occupancy 

sensor, and control wiring.

• 

Notice: Risk of damage to unit. 

Do not 

connect line voltage/mains cable to IEC 

PELV terminals.

Step 1: Install wallbox. 

Mount an  

89 mm deep 4-gang U.S. wallbox on a 

dry, flat indoor surface that is accessible 

and allows for system programming 

and operation. Allow at least 110 mm 

clearance above and below the faceplate 

to ensure proper heat dissipation. 
Allow 25 mm for faceplate overhang on 

all sides. 

Note:

 4-gang wallbox available from 

Lutron; P/N 241400.

Step 2: Check control unit wiring.

 

Earth/ground terminal connection must 

be made as shown in line voltage wiring 

diagrams.

•  Follow all local and national electrical 

codes when installing IEC PELV wiring 

with line voltage/mains wiring.

• Use the rearmost knockouts when pulling 

wires into the wallbox. This will provide 

the most clearance when mounting the 

module.

WARNING!

 

Shock hazard.

 May 

result in serious injury or death. 

Always turn off circuit breaker or 

remove main fuse from power line 

before doing any work. 

Step 3: Connect line voltage and loads 

to control unit.

• Strip 8 mm of insulation off the line 

voltage/mains cables in the wallbox.

• Connect the line voltage/mains, ground, 

and load wires to the appropriate 

terminals on the back of the control unit.

  L: Line/Hot
  N: Neutral
      : Ground
  The recommended installation torque is 

0.6 N

m for line voltage/mains 

connections and 0.6 N

m for the earth/

ground connection.

Notice:

 Proper short circuit and overload 

protection must be provided at the 

distribution panel. You can use up to 

a 20 A maximum circuit breaker with 

adequate short-circuit breaking capacity 

for your installation.

Notice: Risk of damage to unit.

 

The Wallbox Power Module with DALI 

control units must be in stalled by a 

qualified electrician in accordance with 

all applicable regulations and building 

codes. Improper wiring can result 

in damage to control units or oth er 

equipment.

Notice:

 

To avoid overheating and 

possible damage to equipment, do not 

install control units to dim receptacles, 

motor-operated appliances, or 

fluorescent lighting not equipped with 

DALI electronic dimming ballasts, or other 

DALI

 

devices approved for your location. 

Control units are de signed for residential 

and commercial use, for indoor use only.

8 mm

LUTRON

LUTRON

Faceplate overhangs 

wallbox on all sides;  

allow 25 mm

110 mm

ON

OFF

ON

OFF

ON

OFF

Содержание LQR-WPM-16D

Страница 1: ...mbers Ratings 120 240 V 50 60 Hz 100 mA 230 V 50 60 Hz 100 mA Typical Power Consumption 7 W 24 BTUs Power Draw Units PDUs 0 Output DALI Link 18 V 250 mA Codes Install in accordance with all applicable...

Страница 2: ...age terminal can accept one 4 0 mm2 wire Consult Lutron for non dim relay wiring and or load side emergency transfer wiring D1 D1 D2 D2 1 2 3 4 5 6 L N 1 2 3 4 5 6 L N Wiring the Wallbox Power Module...

Страница 3: ...WARNING Shock hazard May result in serious injury or death Always turn off circuit breaker or remove main fuse from power line before doing any work Step 3 Connect line voltage and loads to control u...

Страница 4: ...e live Always turn off circuit breaker or remove main fuse from power line before wiring and servicing the Wallbox Power Module Step 1 Use the wire size chart at right to determine which wire size to...

Страница 5: ...use from power line before doing any work Step 1 Strip 25 mm of insulation from the IEC PELV NECR Class 2 cable Step 2 Strip 7 mm of insulation from each wire in the cable Step 3 Connect the wires to...

Страница 6: ...e on rest the top of the wallplate in the grooves at the top of the unit and press firmly at the bottom corners to secure Step 4 Turn on circuit breaker and check that it does not trip For any feed ci...

Страница 7: ...ou to move through the menu choices The current choice is highlighted on the info screen OK Button The OK button chooses the current highlighted menu choice This will either take you to the next menu...

Страница 8: ...tton to erase all current programming reset and address DALI devices and find sensors on the system 5 Exit programming mode Note After running Build System Zone 4 will control all DALI devices for dia...

Страница 9: ...display at the bottom of the screen and the LEDs for the zone will go on otherwise the info screen will display Unassigned Press the zone raise button to assign the device to that zone Press the zone...

Страница 10: ...he OK button to accept 3 Use the Master buttons to highlight Address All and press the OK button to accept All DALI devices in the system will go to full On As each DALI device is addressed the Wallbo...

Страница 11: ...the third tap Step 2 Keep the Default Scene Button pressed on the third tap for approximately 3 seconds until the LED flashes slowly Step 3 Release the Default Scene Button and immediately triple tap...

Страница 12: ...and shorts HomeWorksR QS only Device is in the Factory Default Settings mode and has not been activated into the system Use the system software to verify activation or reactivate the device and transf...

Отзывы: