Refrigerant piping installation
Connection of High/Low Pressure Common pipe
1. For the High/Low Pressure Common pipe, connect both Main Outdoor Unit and Sub (1, 2) Outdoor Unit to the pipe by
using elbows supplied field.
2. For cutting the pipe, connect the High/Low Pressure Common pipe after removing burrs, dusts and foreign materials
within the pipe. Otherwise, the product may not operate due to sludge within the pipe.
3. For leakage inspection of the work part, pressurize nitrogen gas by 2.94MPa (30kgf/cm
2
).
4. Continue vacuum work after the vacuum degree reaches to 5Torr
5. Open side bar with the hex wrench.
When connecting the pipes from the front of
the outdoor unit, remove part
.
When connecting the pipes from the side of the
outdoor unit, remove part
(the whole "Knock
out" part).
Sub
Outdoor Unit
Main
Outdoor Unit
Sub1
Outdoor
Unit
Sub2
Outdoor
Unit
Main
Outdoor Unit
Knock out
Transmission Line Hole
Power Cable Hole
Pipe Hole
(Side)
(Front)
2 Outdoor Units
3 Outdoor Units
WARNING
After installing the pipe, clog the pipe excavation inlet of the front panel and the side panel
(Wire may be damaged due to entering of rats, animals, etc).