2.9.3 Transfer to customer with explanation
1. Operational step
a) The measurements taken during the test run should be recorded and kept on a test run inspection sheet.
b) Do not forget to record the length of the refrigerant piping and the refrigerant additional charging volume on the plate on
the back of the outdoor unit external notice board, as this information will be required for servicing the system.
c) Explain to the customer how to operate and maintain the equipment and let him try it.
d) Assemble all the relevant diagrams and other printed matter which is required to operate the system and hand over to
the customer (on the spot) and request him to keep it handy.
e) Service contact address.
Complete test run
Make final report
(test run
inspection sheet)
Explain how to
operate and
maintain equipment
Hand over
relevant printed
materials
List of equipment which has been delivered
Installation drawing
It is essential to prepare a control wiring diagram
which clarifies the refrigerant system and the
control system.
1 set of operation manuals
Names of those responsible for the
work (emergency contact address)
Equipment guarantees.
2. Guideline for each installation process
Heat pump 60Hz/R410A
_
37
Installation of
Outdoor Units
SINGLE ZONE
Содержание ATNH24GPLE2
Страница 1: ...SINGLE ZONE Heat pump 60Hz R410A 6CSL0 01B Replaces 6CSL0 01A ...
Страница 2: ...SINGLE ZONE General Information Indoor Units Outdoor Units Design and installation ...
Страница 5: ...SINGLE ZONE Part 1 General information 1 Model Line up 2 Nomenclature 3 Individual Control System ...
Страница 9: ...SINGLE ZONE Part 2 Product data n Indoor units n Outdoor units ...
Страница 14: ...Indoor Units 4 _ Heat pump 60Hz R410A 1 Ceiling cassette 4 way SINGLE ZONE TM Chassis ATNH42GMLE2 LCN427HV ...
Страница 26: ...Outdoor Units 6 _ Heat pump 60Hz R410A 1 DC Inverter SINGLE ZONE SINGLE ZONE U3 Chassis AUUW42GD2 LUU427HV ...